Back to /cathiedwood
s/cathiedwoodGRID STORAGE•May 2
13
votes
384
seen

Tesla Lathrop factory pumping out about 200 Megapacks a week

A single factory is now scaling grid batteries at something like power-plant levels: about 200 Megapacks a week, pointing to 10,000 a year (~40 GWh). Lathrop has been running since late 2022 as a dedicated Megapack site, and recent posts frame it as North America’s largest utility-scale battery plant, with cumulative output already past 10,000 units in 2024 and 15,000 in 2025.

Timeline2
Dec 1

Lathrop Megafactory began operating as a dedicated Megapack production site.

May 2

Fresh posts highlighted Lathrop as North America’s largest utility-scale battery plant with 10,000 Megapacks of annual capacity.

1 comment
May 2
Discussion

1 comment

Sign in to join the discussion